Planning guarantee
The term ‘planning guarantee’ refers to the Government policy that no planning application should spend more than a year with decision-makers, including any appeal.
This means that planning applications themselves should be decided in no more than 26 weeks, allowing for a further 26 weeks to for any appeal. This should only be exceeded following a written agreement with the applicant, setting out the timescale within which a decision is expected.
This is in addition to the statutory time limits which set targets for planning authorities determine planning applications:
- Within 13 weeks for applications for major development.
- Within eight weeks for all other types of development (unless an application is subject to an Environmental Impact Assessment, in which case a 16 week limit applies).
If a valid application is not determined within the statutory period (or such other period as has been agreed) the applicant has a right to appeal to the Secretary of State against non-determination.
If the applicant does not exercised this right of appeal, and the application remains undetermined after 26 weeks, then the fee will be refunded.
Where planning authorities are designated as not adequately performing their function of determining applications, major development may be submitted directly to the Secretary of State. See Special measures designation for under-performing planning authorities for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.