Planning guarantee
The term ‘planning guarantee’ refers to the Government policy that no planning application should spend more than a year with decision-makers, including any appeal.
This means that planning applications themselves should be decided in no more than 26 weeks, allowing for a further 26 weeks to for any appeal. This should only be exceeded following a written agreement with the applicant, setting out the timescale within which a decision is expected.
This is in addition to the statutory time limits which set targets for planning authorities determine planning applications:
- Within 13 weeks for applications for major development.
- Within eight weeks for all other types of development (unless an application is subject to an Environmental Impact Assessment, in which case a 16 week limit applies).
If a valid application is not determined within the statutory period (or such other period as has been agreed) the applicant has a right to appeal to the Secretary of State against non-determination.
If the applicant does not exercised this right of appeal, and the application remains undetermined after 26 weeks, then the fee will be refunded.
Where planning authorities are designated as not adequately performing their function of determining applications, major development may be submitted directly to the Secretary of State. See Special measures designation for under-performing planning authorities for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.